AGOCO - Arabian Gulf Oil Company
Project in progress
Nafoora Oil Field - Tank D-1

- Cleaning and bottom and shell repairing of Crude Oil Tanks
- Inspection
- Painting of Tank’s internal and external surfaces
Replacing of drain pipe lines
Nafoora Oil Field - Installation of Four Separators

- Four (4) out of service separators replaced with new ones
- Testing, Commissioning and Start – Up
Ethylene Plant, RASCO, Ras Lanuf, Libya
- Routine and Preventive Maintenance
- Planning and Execution of Major Overhauls
- Turnaround ETA 2004, Mechanical Works, 40 Workers
- Turnaround ETA 2007, Mechanical and Instrument Works, 100 Workers
Polyethylene Plant, RASCO Ras Lanuf, Libya
- Maintenance Contract with HYUNDAI, 30 Months
- Routine Daily Maintenance Jobs
- Establish Preventive Maintenance Programs,
- Prepare and execute the first Major Plant Turnaround
Utility Plant, RASCO Ras Lanuf, Libya
- Desalination Units Reconstruction of chemicals pipe lines,
- Replace CS pipes with BONDSTRAND pipes
Polyethylene Plant Ras Lanuf, Libya
- Contract with HYUNDAI, 6 months
- Commissioning and start-up of C 4 cryogenic tank
- Turnaround PETA 2010, Mechanical Works, Rotating Equipment and Instrument Works
- Engaged 56 Workers, completed in April 2010
Ethylene Plant Ras Lanuf, Libya
- Turnaround ETA 2010, Mechanical Works, Rotating Equipment and Instrument Works
- Engaged 140 Workers, completed in April 2010
Attahaddy Gas Field Development Project (HYUNDAI)
- Commissioning of Rotating Equipment
- Corrections of pipe lines punch lists
- Pipe lines hydro testing
- Commissioning of process and preparation for Start-up
Azzawiya Refinery, Libya, 2008
- Design and construction of Twin Warehouse 5000 m2
- Underground Piping, Concrete Foundations, Access Roads,5000 m2 of Concrete Flooring,
- Electrical, Fire-fighting and Shelving System are included
Azzawiya Refinery, Libya, 2008
Overhauling of heaters 21/121-H4 &110-H1
Turnaround 2010. 95 Workers engaged
G.C.C.I Abukammash Chemical Complex, Libya Ethylene Storage plant
Finished 2006
Design improvement of Strip Anchors and Annular Ring
Repairing of Annular Rings, Shells and Roofs on two Ethylene Storage Tanks
Sand blasting and painting of Tanks
G.C.C.I Abukammash Chemical Complex, Libya
Overhauling of Ethylene Refrigeration Compressors
Completely dismount, check of all dismounted parts with detailed measuring,
Raising order for necessary spare parts, assembling compressors and el. motors,
Check all shout down system, make commissioning and start up.
After six years compressors and refrigeration are in function and systems are in full operation
SARIR Oil Field
Cleaning and bottom repairing/replacing of Crude Oil Tanks, (Annual turnaround 2007.)
Painting of Tank’s internal and external surfaces
Replacing of Furnace Coils in three Furnaces,
Relocate two Oil Separators from GS-1 to GC-2&GC-3

AGOCO - Messla Oil Field, Libya

Repairing and Painting of four Water Tanks

Brega Marketing, Ras El Mungar - Benghazi
- Repairing three storage tank
- Replace damaged bottom plates, roof repairing
- Replace annular ring and one meter of the shell
- Painting of the tanks
MAA Refinery –KNPC Kuwait
- Replacement of 12 Pipe Lines in MAA Refinery
- 2600 tons of Pipes, sizes of lines are from 36” to 6”
- Contract price 8.5 million USD
- Project duration 12 months
Refinery Port Harcourt - Nigeria
- 2 year Contract
- Planning and Execution Refinery turnaround
- Mechanical and Electrical activities
Pancevo and Novi Sad Refineries, Yugoslavia
- Daily maintenance, Preventive maintenance and Turnaround
- Reconstruction of Vacuum Distillation and Tank Farm, after bombing of Yugoslavia
Refinery CPC RFCC Taiwan
- Contract with LG Eng & Const. Corporation
- Commissioning and Process preparation for Start-up of new refinery, contract duration 6 months